View Street Sewer Relining

Sewer relining works in sensitive conditions

Partial collapse of a sewer line was identified within the footpath along View Street adjacent to the support columns of a heritage listed balcony. Replacement would require the need for open excavation, and significant structural support of the balcony during the works, risking settlement and damage to the heritage listed structure.

By further analysing the CCTV footage, Interflow was able to develop a methodology which minimised the length of sewer to be replaced via open trenching, which subsequently removed the need to excavate alongside the balcony support columns. The proposed approach focussed on replacing the pipelines worst collapsed section through open trenching.

Following this, Expanda liner was wound through the excavation from maintenance hole to maintenance hole. This gave the lining crew greater visibility and control during relining and ensured the remaining damaged (sensitive) sections of sewer pipe were not dislodged during relining works, minimising the risk of further collapse and blockages.

Wastewater

Expanda

2018

Once the bungs were installed, the vac truck sucked out the manhole periodically, whilst the crew set Due to the numerous existing services within the vicinity and the restricted space available to work in the area, Interflow used a vacuum truck for hydro-excavation.

A structural Expanda spiral wound liner was used to renew the full length of the sewer in these two sections, and joined in the middle via PVC pipework and couplers. Interflow used stabilised sand for backfill material to ensure there would be no subsidence post-completion of works, which could risk damage to the balcony and settlement of the asphalt reinstatement.

The challenge

These works were located within a section of footpath along View Street in Bendigo, common to high volumes of pedestrian traffic. A initial condition assessment of the sewer pipe identified significant structural cracks, ingress of large tap roots and a collapsed section mid-way between two manholes.

Due to the extent of existing damage, a large section required replacement via open trenching prior to relining. Any excavation would undermine the support column foundations of a nearby heritage listed balcony structure. In this instance, significant structural support of the balcony was required at considerable cost. To overcome this, a temporary propping system was designed to ensure there was no risk of foundation movement or settlement, both during and after the works.

The solution

The damaged section of the pipe was repaired and the sewer relining of this entire line was completed using Expanda spiral wound liner without imposing risk to the support structure of this heritage listed balcony.

Conclusion

This project was successfully completed without incident in these complex and sensitive conditions. The works were completed in the Bendigo CBD, and received no complaints or concerns raised by the public during the works. Interflow was able to have this work completed within a week, significantly faster than if the service was otherwise replaced via means of a dig-lay-backfill method.

Customer
Coliban Water

Value
Enquire

Location
Echuca, VIC

Status
Complete

Enquire about this project

Related resources

Technical Specs

Technical specifications of the products used

Papers

News featuring this project

News featuring this project

All external resources related to this project

Related news