Anstruther Street Bypass Pumping

Bypass pumping to allow infrastructure upgrades

Interflow used a custom-designed steel casing tube to Infrastructure upgrades were required at the Anstruther Pump Station, including the removal and replacement of a twin set of 10” pumps and associated pipework inside a 12m deep dry well. The system was directly connected to Echuca’s sewer system and was subsequently unable to be shut down for these upgrade works to commence.

Interflow was approached by the client to provide support to their mechanical and electrical subcontractor in the form of setting up a bypass pump arrangement. This allowed the upgrades to be implemented within a live sewer network in a period of one week.

In order to create the bypass, a vacuum truck was used to pump down the network sewer. This allowed the crew to insert pneumatic bungs within the connecting pipes of an upstream manhole and the pump station wet well (at 12m deep).

Wastewater

Bypass pumping

2019

Once the bungs were installed, the vac truck sucked out the manhole periodically, whilst the crew set up the dual bypass pumps and temporary transfer pipework. Suction pipes were inserted into the manhole and delivery pipework connected to an above ground flanged assembly (downstream of the Pump Station and isolated via an inline gate valve), subsequently bypassing the work zone.

These pumps had been suitably selected, as to maintain the average and peak flows expected within the system throughout the duration of works. The pumps operated on a series of high and low level floats, allowing them to maximise their efficiency during pumping and minimise disturbance to the nearby residents.

The challenge

The existing sewer network in this location was renowned for high gas levels and confined spaces. The pumping arrangement needed to bypass a sewer line 12m deep, whilst maintaining double isolation for protection of the workers inside the dry well.

The solution

For safe access into the confined space, the high gas levels needed to be reduced. This was achieved by removing the top manhole increment which enabled better ventilation. Extraction fans were also inserted to provide a source of clean air.

Double isolation was provided by inserting bungs from both ends of the pipe between the manhole and the Pump Station wet well. When the pumps were removed, blank flanges were then bolted onto the flanged pipework inside the wet well which mechanically provided isolation in addition to the two bungs.

Conclusion

On completion of the pump replacement works, the bypass pumps were dismantled in a reverse order as they were installed, which allowed Interflow to pack up and reinstate the site. There were no issues with the pumps during the works, no complaints from nearby residents, and the client’s mechanical and electrical subcontractor was provided with safe access to successfully complete their pump replacement works.

Customer
Coliban Water

Value
Enquire

Location
Echuca, VIC

Status
Complete

Enquire about this project

Related resources

Technical Specs

Technical specifications of the products used

Papers

News featuring this project

News featuring this project

All external resources related to this project

Related news